From Tuesday 3 November 2026, the City of Cockburn is introducing a new TMP application process.
All TMP applications will need to be submitted online. A fee of $300 will apply with payment required at the time of submission.
A new application portal will be opened on this website page from that date.
Duty of care
Any Person Conducting a Business or Undertaking (PCBU) in connection with or pursuant to temporary traffic management or any works on a road, has a 'duty of care', so far as is reasonably practicable, that the health and safety of workers who work for the PCBU or whose activities in carrying out work are influenced or directed by the PCBU, are not exposed to health and safety risks arising from that business or undertaking.
A PCBU must ensure, so far as reasonably practicable, that other road users are not exposed to health and safety risks arising from any Temporary Traffic Management (TTM) business or undertaking. A PCBU includes all types of working arrangements such as crown agencies, organisations, companies, principals, contractors and sub-contractors.
The Work Health and Safety Act specifically requires all PCBUs to ensure, so far as is reasonably practicable, the health and safety of:
- workers engaged or caused to be engaged by the person
- workers whose activities in carrying out the work are influenced or directed by the person while the workers are at work in the business or undertaking
- people who may be at risk from work carried out by the business or undertaking (including road users in case of a at roadwork sites).
As part of this 'duty of care' any PCBU undertaking works within a road reserve that is under the care, control and management of the City of Cockburn that presents a risk to, or impacts on road users & workers is required to have approval to implement a Traffic Management Plan (TMP) from the City of Cockburn in accordance with the Main Roads WA (MRWA) Traffic Management for Works on Roads Code of Practice (CoP).
Traffic Management Plan (TMP) Submissions
The Traffic Management Plan preparation shall be carried out in accordance with the current MRWA CoP, and shall be submitted to the City in advance of the works to allow for sufficient time to carry out assessment, authorisation, and any required notification before implementation.
Assessment timeframes
The minimum Traffic Management Plan assessment lead time that the City requires is 10 business days (Monday to Friday excluding public holidays) for low complexity works were no notification to other stakeholders is required.
Note for more complex works further guidance will be given on a case by case basis during the initial review. Further, the following (provisional) minimum assessment lead times are recommended by the City:
- for low complexity works – 10 business days (15 business days if notification is required)
- for complex works – 20 business days (not including any notification period that may be required).
- for low impact road closures less than four weeks - 10 business days (15 business days if notification is required).
- for high impact road closures and road closures exceeding four weeks the City’s Traffic and Transport unit shall be contacted 60 business days before submission for in principal support.
- for event TMPs, in addition to the above assessment times, event organisers may need to consider impacts on assessment times caused by other approvals required. Please refer to the City’s Guide to Running a Community Event.
Submission requirements
All submission must contain the following documentation:
- A copy of approval for the works from the relevant approving authority e.g. for works on utilities the relevant utility owner, for works on a City asset within the road reserve the relevant City Service Unit, etc.
- A copy of a Certificate of Currency for Public Liability Insurance of sufficient value to cover risk associated with the works and traffic management implementation.
- A Traffic Management Plan designed by an appropriately accredited Traffic Management Plan designer as per the Main Roads WA (MRWA) Traffic Management for Works on Roads Code of Practice (CoP), and as a minimum reviewed by a secondary holder of Advanced Worksite Traffic Management Accreditation (AWTM) or higher level of accreditation if required by the CoP.
Fees
A non-refundable administration fee of $300 applies to Traffic Management Plan (TMP) assessments, to be paid at the time of submission.
GST not applicable.
Apply for a TMP
All Traffic Management Plan (TMP) applications must be submitted online.
Submit your application
For more information in regards to Traffic Management Plan submissions please contact the City’s Traffic and Transport Service Unit on 08 9411 3444 or email
[email protected]